Hal 25 is ready and set as our new packaging, assembly and expedition department. We now have a lots of space for storage, large assembly orders and packaging our machined aluminium and plastic parts for our customers.





Timeline of Hall 25:
November 2024: Site is prepared for construction.
December 2024: Construction is largely complete.
January 2025: Hall is ready, doors and frames stil lneed to be installed.
End of January 2025: Skating party, festive opening of our new hall.
March 2025: Electricity finished. Ready for movement of equipment.
April 2025: Packaging/assembly department fully equipped and in full use.
The new hall is already in use. The packaging / assembly department is running at full speed! Products are, as always, neatly packaged for transport. The machined parts must, of course, arrive at the customer undamaged. The packaging differs per product, we already have a lot of experience with that.